Palisade Modular Systems
Oswego Community Tranche
The same notes as the flagship offering, in $500 denominations, reserved for New York residents.
A host community tranche running concurrently with the Reg A+ offering under Rule 152, restricted to residents of New York State under Rule 147A. Same seniority and same collateral as the flagship notes, with a 25 basis point premium and a $500 minimum, because the people who live beside the plant should be able to own a piece of it on better terms than the institution that never visits.
Running concurrently over the same project
Rule 152 permits an issuer to run more than one offering at the same time. The same reactor backs both, on different rails, with different eligibility.
$2,648,500 committed of $4,000,000
$1,812,000 released · 66% subscribed
- Minimum
- $500
- Target coupon
- 7.50%
- Term
- 7 yr
- Investors
- 1,637
$500 per unit
Annual, fixed
Closes November 30, 2026 · 78 days remaining
Sign in to see your limit
- Eligibility depends on residency, accreditation status and how much you have already invested this year.
- You can read everything about this offering without an account. Committing capital requires one.
Demo · viewing as
Browsing without an account. Everything is visible; nothing is purchasable until you verify who and where you are.
Or answer the questions yourselfNo money will move
No payment processor is connected. The commitment flow runs end to end, through amount, agreement, signature and receipt, and records a simulated position rather than a charge.
TRL assessment
8
Technology readiness level, 1 to 9
Confidence band 7.6 – 8.3
Module one is complete, fueled and qualified, and ITAAC closure is materially advanced with 87 of 104 criteria accepted. The band is narrow because the evidence is unusually direct: an issued combined license and a witnessed integrated systems test leave little to infer. The score stops short of 9 because no module has yet generated electricity for the grid. What is left is first-of-a-kind construction cost uncertainty on modules two and three, which is a commercial risk rather than any doubt about the design.
At TRL 8, the ladder permits Fixed-rate note or Municipal mini-bond and releases up to 90% of committed capital. This offering is structured as a fixed-rate note, which is consistent with that band.
Signed and published
- Reviewer
- Dr. Helena Vargas-Mbeki
- Credential
- PE, Nuclear; former NRC senior reactor analyst
- Signed
- July 14, 2026
- Published
- July 15, 2026
- Methodology
- v1.4
- Model
- ci-trl-2026.06
- Generated
- Jul 9, 2026
Evidence
Every score cites the documents it was derived from, with the weight each carried. An assessment without evidence is an opinion.
| Source | Document | Date | Weight |
|---|---|---|---|
| Operating license | Combined license issued, Oswego Units 1–3 NRC Docket 52-0xx, license NPF-xxx Authorizes construction and conditional operation of three modules subject to ITAAC closure. | Nov 19, 2024 | 34% |
| ITAAC closure | ITAAC closure notifications, 87 of 104 accepted Issuer submittal series, NRC acknowledgement letters Remaining seventeen criteria relate to module two and three installation, not to design adequacy. | Jun 30, 2026 | 29% |
| Independent test report | Integrated systems test, module one, third-party witnessed Independent verification report, ANSI/ANS-3.5 protocol Natural circulation decay heat removal demonstrated within 4% of predicted performance. | Feb 11, 2026 | 22% |
| Supplier contract | Executed forging and vessel supply agreements Two suppliers, ASME Section III scope, firm pricing Long-lead components for modules two and three under firm fixed price with delivery windows. | Jan 22, 2026 | 15% |
Score history
A score changes on the day a reviewer signs a new assessment, which is why this is a step line rather than a curve.