Reg A+TRL76.47.5Tier IIOpen

Bridgman Units 1 and 2 Completion

Senior notes on 2,260 MWe of gigawatt-scale capacity where the containment concrete was poured in 1982.

Two units were 62% and 41% complete when the program was canceled in 1982. The containment structures, cooling water intake and switchyard already exist, and the site has an operating history and a community that wants the jobs back. Completing abandoned construction is the cheapest gigawatt anyone can buy, provided the concrete passes inspection, which is what the first tranche paid to establish.

Bridgman Generating Station · Bridgman, MIConstruction permit issuedEscrow: Meridian Trust, N.A.
TRL 7 of 9, band 6.4 to 7.5, signed by Dr. Helena Vargas-Mbeki, PE, Nuclear; former NRC senior reactor analyst, on Jun 10, 2026.See the evidence it rests on

Running concurrently over the same project

Rule 152 permits an issuer to run more than one offering at the same time. The same reactor backs both, on different rails, with different eligibility.

$52,875,000 committed of $75,000,000

$37,012,500 released · 71% subscribed

Released to the issuerCommitted, held in escrowRemaining
Minimum
$1,000

$100 per unit

Target coupon
6.95%

Annual, fixed

Term
10 yr
Investors
5,741

Closes March 31, 2027 · 199 days remaining

Sign in to see your limit

  • Eligibility depends on residency, accreditation status and how much you have already invested this year.
  • You can read everything about this offering without an account. Committing capital requires one.
Open an account
Open an account to invest

Demo · viewing as

Browsing without an account. Everything is visible; nothing is purchasable until you verify who and where you are.

Or answer the questions yourself

No money will move

No payment processor is connected. The commitment flow runs end to end, through amount, agreement, signature and receipt, and records a simulated position rather than a charge.

7

Technology readiness level, 1 to 9

Confidence band 6.47.5

The reactor design is a proven operating technology, so the TRL question here is not about physics but about forty-year-old concrete. An independent structural assessment has found the containment and basemat sound, which is what supports a level 7 rather than something lower. The band is wider than a normal operating asset because degradation findings during completion remain possible, and gigawatt-scale construction cost risk remains whatever the engineering confidence, which is a commercial question this scale does not answer.

At TRL 7, the ladder permits Senior note and releases up to 70% of committed capital. This offering is structured as a senior note, which is consistent with that band.

Signed and published

Reviewer
Dr. Helena Vargas-Mbeki
Credential
PE, Nuclear; former NRC senior reactor analyst
Signed
June 10, 2026
Published
June 11, 2026
Methodology
v1.4
Model
ci-trl-2026.06
Generated
Jun 5, 2026

Evidence

Every score cites the documents it was derived from, with the weight each carried. An assessment without evidence is an opinion.

SourceDocumentDateWeight
Independent test report

Independent structural and materials assessment, containment and basemat

Third-party engineering assessment, core sampling and ultrasonic survey

Concrete compressive strength and rebar condition within original design specification at all sampled locations.

Apr 8, 202633%
NRC docket

Construction permit reinstated on amended docket

NRC docket amendment, original construction permit 50-xxx

Permit reinstated subject to updated seismic and aging management analysis.

Dec 16, 202529%
Supplier contract

Reactor vessel and steam generator supply agreements

Two suppliers, firm fixed price with delivery windows

Long-lead components ordered with liquidated damages for late delivery.

Feb 25, 202624%
Supplier contract

Power purchase agreements, three midwestern utilities

Executed 25-year contracts

Contracted output covers 88% of expected net generation.

Jan 19, 202614%

Score history

A score changes on the day a reviewer signs a new assessment, which is why this is a step line rather than a curve.

13579Mar 2024Dec 2025Jun 2026