Palisade Oswego Unit 1

Fixed-rate notes on a three-module SMR with ITAAC closure underway and twenty years of contracted offtake.

Palisade is building three 77 MWe modules on the site of a retired coal station in Oswego, New York. Module one is complete and qualified; inspections, tests, analyses and acceptance criteria are being closed against the combined license. Proceeds fund the second and third modules. Notes pay a fixed 7.25% annually with principal at year seven, secured by a first lien on the module assets and backstopped by two twenty-year power purchase agreements.

Oswego Energy Center · Oswego, NYITAAC in progressEscrow: Meridian Trust, N.A.
TRL 8 of 9, band 7.6 to 8.3, signed by Dr. Helena Vargas-Mbeki, PE, Nuclear; former NRC senior reactor analyst, on Jul 14, 2026.See the evidence it rests on

Running concurrently over the same project

Rule 152 permits an issuer to run more than one offering at the same time. The same reactor backs both, on different rails, with different eligibility.

$31,240,000 committed of $48,000,000

$21,400,000 released · 65% subscribed

Released to the issuerCommitted, held in escrowRemaining
Minimum
$1,000

$100 per unit

Target coupon
7.25%

Annual, fixed

Term
7 yr
Investors
2,184

Closes November 30, 2026 · 78 days remaining

Sign in to see your limit

  • Eligibility depends on residency, accreditation status and how much you have already invested this year.
  • You can read everything about this offering without an account. Committing capital requires one.
Open an account
Open an account to invest

Demo · viewing as

Browsing without an account. Everything is visible; nothing is purchasable until you verify who and where you are.

Or answer the questions yourself

No money will move

No payment processor is connected. The commitment flow runs end to end, through amount, agreement, signature and receipt, and records a simulated position rather than a charge.

8

Technology readiness level, 1 to 9

Confidence band 7.68.3

Module one is complete, fueled and qualified, and ITAAC closure is materially advanced with 87 of 104 criteria accepted. The band is narrow because the evidence is unusually direct: an issued combined license and a witnessed integrated systems test leave little to infer. The score stops short of 9 because no module has yet generated electricity for the grid. What is left is first-of-a-kind construction cost uncertainty on modules two and three, which is a commercial risk rather than any doubt about the design.

At TRL 8, the ladder permits Fixed-rate note or Municipal mini-bond and releases up to 90% of committed capital. This offering is structured as a fixed-rate note, which is consistent with that band.

Signed and published

Reviewer
Dr. Helena Vargas-Mbeki
Credential
PE, Nuclear; former NRC senior reactor analyst
Signed
July 14, 2026
Published
July 15, 2026
Methodology
v1.4
Model
ci-trl-2026.06
Generated
Jul 9, 2026

Evidence

Every score cites the documents it was derived from, with the weight each carried. An assessment without evidence is an opinion.

SourceDocumentDateWeight
Operating license

Combined license issued, Oswego Units 1–3

NRC Docket 52-0xx, license NPF-xxx

Authorizes construction and conditional operation of three modules subject to ITAAC closure.

Nov 19, 202434%
ITAAC closure

ITAAC closure notifications, 87 of 104 accepted

Issuer submittal series, NRC acknowledgement letters

Remaining seventeen criteria relate to module two and three installation, not to design adequacy.

Jun 30, 202629%
Independent test report

Integrated systems test, module one, third-party witnessed

Independent verification report, ANSI/ANS-3.5 protocol

Natural circulation decay heat removal demonstrated within 4% of predicted performance.

Feb 11, 202622%
Supplier contract

Executed forging and vessel supply agreements

Two suppliers, ASME Section III scope, firm pricing

Long-lead components for modules two and three under firm fixed price with delivery windows.

Jan 22, 202615%

Score history

A score changes on the day a reviewer signs a new assessment, which is why this is a step line rather than a curve.

13579Sep 2023Dec 2024Aug 2025Jul 2026