Capital release

Committed capital sits with the escrow agent and moves to you one tranche at a time, each against a milestone certified by somebody with no economic interest in the release. It is slower than taking the whole raise at close, and it is the reason investors will fund a technology at this stage at all.

Released to you
$23,212,000

Against certified milestones

Still held in escrow
$10,676,500

Yours tranche by tranche, not at close

Requests outstanding
0

With the certifier, awaiting signature

Oswego Unit 1

$33,888,500 committed across 2 offerings

  1. Combined license issued

    Capital released
    TRL target
    TRL 7
    Cumulative release
    70% · $23,721,950
    Certified
    May 20, 2026

    Verified by: NRC license issuance and supplier contracts executed

    Certifier: Thornbury Technical Certification

  2. Module one complete and qualified

    Certified
    TRL target
    TRL 8
    Cumulative release
    90% · $30,499,650
    Certified
    July 28, 2026

    Verified by: ITAAC closure for module one; integrated systems test witnessed

    Certifier: Thornbury Technical Certification

  3. Full ITAAC closure, all three modules

    Pending
    TRL target
    TRL 8
    Cumulative release
    95% · $32,194,075
    Target
    June 30, 2028

    Verified by: NRC final determination of ITAAC closure

  4. Commercial operation

    Pending
    TRL target
    TRL 9
    Cumulative release
    100% · $33,888,500
    Target
    March 31, 2029

    Verified by: Commercial operation date certificate; metered output to grid